Construction Projects & Street/Road Closings

CONSTRUCTION NOTICES

***ALL Work scheduled subject to change pending weather**

Morristown Train Station Improvements – Phase II

  • Contractor: HBC Company, Inc.
  • Work Description: Installation of new streetscape light poles
  • Location: Lafayette Avenue sidewalk adjacent to NJ Transit train trestle
  • Work Hours: 7:00 am – 4:00 pm, Limited to 9:00 am to 3:00 pm for work in roadway, Monday through Friday
  • Project Start: Monday 4/7
  • Estimated Duration: 2 weeks
  • Special Conditions:
    • Sidewalk in work area to be closed during work hours.
    • One lane to be closed during work hours (9:00 am to 3:00 pm).
    • All businesses, homes, and adjacent streets in the area will remain accessible.

Lidgerwood Park Restroom Improvements

  • Contractor: RSA Home Improvements
  • Work Description: Interior renovation of bathrooms
  • Location: Lidgerwood Parkway
  • Work Hours: 7:00 am - 4:30 pm, Monday through Friday
  • Project Start: Ongoing
  • Completion Date: Late May 2025
  • Special Conditions:
    • Restrooms are closed until completion.
    • Construction trucks, equipment, and workers entering and working at/around restroom building.

 

Burnham Park Concession Building Restroom Improvements

  • Contractor: RSA Home Improvements
  • Work Description: Interior renovation of bathrooms
  • Location: Scherzer Way
  • Work Hours: 7:00 am - 4:30 pm, Monday through Friday
  • Project Start: Ongoing
  • Completion Date: Late May 2025
  • Special Conditions:
    • Restrooms are closed until completion.
    • Construction trucks, equipment, and workers entering and working at/around restroom building.

Concrete Sidewalk Grinding Services

  • Contractor: Waters & Bugbee General Contractors
  • Work Description: Grinding of uneven concrete sidewalk sections to remove tripping hazards
  • Location: Various streets throughout the town
  • Work Hours: 7:00 am – 5:00 pm, Monday through Friday
  • Project Start: Ongoing
  • Estimated Duration: 2 year contract (2025-2026)
  • Special Conditions:
    • Work to occur periodically throughout the town as funds become available.
    • Select sidewalk sections to be closed during grinding operations.
MEDICAL_COVID_-_19_GENERIC_Customer_Letter__MORRISTOWN_Page_1.jpg

2021 PSE&G Gas System Upgrade Information

PSE&G will be replacing old gas pipes on various Morristown streets with new piping – in an effort to provide the continued safety and reliability of your gas service. Please click on the images below for project details and for a list of affected streets.